Sun Village 2026
Hello Residents!
Week of 6/1/26: This week, we will continue to prep and paint the walls in the areas marked in BLACK. Please make sure that vegetation, decor, lights and critter fencing is removed from the iron so that we have access to paint. Please leave side gate unlocked and secure pets indoors. Feel free to call our office with any questions.

Week of 5/26/26: This week, we will prep and paint the walls in the areas marked in BLACK. We will continue completing iron repair at the homes circled in BLACK. Please make sure that vegetation, decor, lights and critter fencing is removed from the iron so that we have access to paint. Please leave side gate unlocked and secure pets indoors. Our office will be closed for Memorial Day on Monday, 5/25. The crew will be back onsite on Tuesday, 5/26. Feel free to call our office with any questions.


Week of 5/18/26: This week, we will be painting view fencing in the areas marked in BLACK. We will also prep and paint the walls in the areas marked in DARK BLUE. We will continue completing iron repair at the homes circled in BLACK. Please make sure that vegetation, decor, lights and critter fencing is removed from the iron so that we have access to paint. Please leave side gate unlocked and secure pets indoors. Feel free to call our office with any questions.


Week of 5/11/26: This week, we will be painting view fencing in the areas marked in BLACK. We will continue completing iron repair at the homes circled in BLACK. Please make sure that vegetation, decor, lights and critter fencing is removed from the iron so that we have access to paint. Please leave side gate unlocked and secure pets indoors. Feel free to call our office with any questions.


Week of 5/4/26: This week, we be painting view fencing in the areas marked in BLACK. We will also prep and paint walls in the areas marked in DARK BLUE. We will continue completing iron repair at the homes circled in BLACK. Please make sure that vegetation, decor, lights and critter fencing is removed from the iron so that we have access to paint. Please leave side gate unlocked and secure pets indoors. Feel free to call our office with any questions.


Week of 4/27/26: This week, we be painting view fencing in the areas marked in BLACK. We will also continue completing iron repair at the homes circled in BLACK. Please make sure that vegetation, decor, lights and critter fencing is removed from the iron so that we have access to paint. Please leave side gate unlocked and secure pets indoors. Feel free to call our office with any questions.


Week of 4/20/26: This week, we will start to prep and paint the walls in the areas marked in BLACK. We will also continue completing iron repair at the homes circled in BLACK. Please make sure that vegetation, decor, lights and critter fencing is removed from the iron so that we have access to paint. Please leave side gate unlocked and secure pets indoors. Feel free to call our office with any questions.


Week of 4/13/26: This week, we will continue to prep and paint the walls and paint view fencing in the areas marked in GREEN. We will also be completing iron repair at the homes circled in BLACK. Please make sure that vegetation, decor, lights and critter fencing is removed from the iron so that we have access to paint. Please leave side gate unlocked and secure pets indoors. Feel free to call our office with any questions.


Week of 4/6/26: This week, we will be painting view fencing in the areas marked in BLACK. We will also start prepping walls in the areas marked in GREEN. Please make sure that vegetation, decor, lights and critter fencing is removed from the iron so that we have access to paint. Please leave side gate unlocked and secure pets indoors. Feel free to call our office with any questions.

Week of 3/30/26: This week, we will be painting view fencing in the areas marked in BLACK. On Monday, 3/30, we will also continue completing iron repair as needed. Please make sure that vegetation, decor, lights and critter fencing is removed from the iron so that we have access to paint. Please leave side gate unlocked and secure pets indoors. Feel free to call our office with any questions.

Week of 3/23/26: This week, we will be prepping and painting walls in the areas marked in BLACK. We will also continue completing iron repair as needed. Please make sure that vegetation, decor, lights and critter fencing is removed from the iron so that we have access to paint. Please leave side gate unlocked and secure pets indoors. Feel free to call our office with any questions.

Week of 3/16/26: This week, we will be painting view fencing in the areas marked in BLACK. We will also be completing iron repair on the view fencing in the areas circled in BLACK. Please make sure that vegetation, decor, lights and critter fencing is removed from the iron so that we have access to paint. Please leave side gate unlocked and secure pets indoors. Feel free to call our office with any questions.


Week of 3/9/26: This week, we will be painting the walls in the areas marked in BLACK, following the arrows. We will also be prepping the walls in the areas marked in BLUE. Feel free to call our office with any questions.

Week of 3/2/26: This week, we will be painting view fencing in the areas marked in DARK BLUE following the arrows. We will also be prepping the walls in the areas marked in BLACK, following the arrows. Please make sure that vegetation, decor, lights and critter fencing is removed from the iron so that we have access to paint. Please leave side gate unlocked and secure pets indoors. Feel free to call our office with any questions.

Week of 2/23/26: This week, we will be painting view fencing in the areas marked in RED following the arrows. Please make sure that vegetation, decor, lights and critter fencing is removed from the iron so that we have access to paint. Please leave side gate unlocked and secure pets indoors. Feel free to call our office with any questions.

Week of 2/16/26: This week, we will be prepping and painting walls in the areas marked in DARK BLUE following the arrows. Feel free to call our office with any questions.

Week of 2/9/26: We are excited to be starting the painting project in Sun Village this week! This week, we will be prepping and painting walls in the areas marked in RED following the arrows. Feel free to call our office with any questions.