Week of 7/20/26:  We have completed painting the walls in Phase 1 East and Phase 1 West.  This week, we will complete painting the walls in Phase 2 East and Phase 2 West. We will also start painting the wall caps in Phase 1 East and Phase 1 West.  Feel free to call our office with any questions.

Week of 7/13/26:  The culverts in the community have been completed.  This week, we will start prepping and painting the walls in Phase 1 East (YELLOW) and Phase 1 West (BLUE).  Feel free to call our office with any questions.

Week of 7/6/26: We are excited to be starting the painting project in Arabella!  This week, we will start painting the culverts in the community.  We will also be power washing the walls in the areas marked in RED.  Feel free to call our office with any questions.