Eagle Mountain Phase 1
Hello Residents!
We have completed the painting project in Eagle Mountain Phase 1. We appreciate you and thank you for choosing Titan Painting for all of your painting needs!
Week of 1/26/26: This week, we will be painting view fencing for the homes that have had to be skipped for various reasons during the project (snake fencing, vegetation, unsecured pets, etc.). Please make sure that vegetation, decor, lights and critter fencing is removed from the iron so that we have access to paint. Please leave side gate unlocked and secure pets indoors. Feel free to call our office with any questions.
Week of 1/19/26: Our crew will not be onsite this week. The crew will return to complete the project the week of 1/26/26. Feel free to call our office with any questions.
Week of 1/12/26: This week, we will continue to paint community monuments, mailboxes and miscellaneous community areas. Feel free to call our office with any questions.
Week of 1/5/26: This week, we will be painting the view fencing in Parcel 6 in the areas marked in RED. We will also be painting community monuments and mailboxes throughout the Eagle Mountain community. Please make sure that vegetation, decor, lights and critter fencing is removed from the iron so that we have access to paint. Please leave side gate unlocked and secure pets indoors. Feel free to call our office with any questions.

Week of 12/22/25 and 12/29/25: Titan Painting will be closed for the holidays from 12/22/25 – 1/2/26. The crew will return onsite on Monday, 1/5/26. Happy Holidays!
Week of 12/15/25: This week, we will be painting the view fencing in the areas marked in RED. Please make sure that vegetation, decor, lights and critter fencing is removed from the iron so that we have access to paint. Please leave side gate unlocked and secure pets indoors. Feel free to call our office with any questions.

Week of 12/8/25: This week, we will be painting the walls in Parcel 6 in the areas marked in ORANGE and painting the view fencing in the areas marked in RED. Please make sure that vegetation, decor, lights and critter fencing is removed from the iron so that we have access to paint. Please leave side gate unlocked and secure pets indoors. Feel free to call our office with any questions.

Week of 12/1/25: This week, we will be painting the view fencing in the areas marked in RED. Please make sure that vegetation, decor, lights and critter fencing is removed from the iron so that we have access to paint. Please leave side gate unlocked and secure pets indoors. Feel free to call our office with any questions.

Week of 11/24/25: Unfortunately, we were rained out the week of 11/17/25. So, this week we will be painting view fencing in Parcel 6 in the areas marked in RED. Please make sure that vegetation, decor, lights and critter fencing is removed from the iron so that we have access to paint. Please leave side gate unlocked and secure pets indoors. Our crew will be onsite on Monday, 11/24-Wednesday, 11/26 from 6am-4pm. We will be closed for Thanksgiving on Thursday, 11/27-Friday, 11/28. Feel free to call our office with any questions.

Week of 11/17/25: This week we will be painting view fencing in Parcel 6 in the areas marked in RED. Please make sure that vegetation, decor, lights and critter fencing is removed from the iron so that we have access to paint. Please leave side gate unlocked and secure pets indoors. Feel free to call our office with any questions.

Week of 11/10/25: This week we will be painting view fencing in Parcel 6 in the areas marked in RED. We will also be prepping and painting walls in Parcel 6 in the areas marked in ORANGE. Please make sure that vegetation, decor, lights and critter fencing is removed from the iron so that we have access to paint. Please leave side gate unlocked and secure pets indoors. Feel free to call our office with any questions.

Week of 11/3/25: This week we will be painting view fencing in Parcel 7 in the areas marked in RED. We will also be prepping and painting walls in Parcel 6 in the areas marked in ORANGE. Please make sure that vegetation, decor, lights and critter fencing is removed from the iron so that we have access to paint. Please leave side gate unlocked and secure pets indoors. Feel free to call our office with any questions.


Week of 10/27/25: This week we will be painting view fencing in Parcel 7 in the areas marked in RED. Please make sure that vegetation, decor, lights and critter fencing is removed from the iron so that we have access to paint. Please leave side gate unlocked and secure pets indoors. Feel free to call our office with any questions.

Week of 10/20/25: This week, we will be prepping and painting the walls in Parcel 7 in the areas marked in RED. Please feel free to call our office with any questions.

Week of 10/13/25: This week we will be painting view fencing in Parcel 4 in the areas marked in RED. Please make sure that vegetation, decor, lights and critter fencing is removed from the iron so that we have access to paint. Please leave side gate unlocked and secure pets indoors. Feel free to call our office with any questions.

Week of 10/6/25: This week we will continue painting view fencing in Parcel 8 in the areas marked in RED. We will also be prepping and painting the walls in Parcel 4 in the areas marked in RED. Please make sure that vegetation, decor, lights and critter fencing is removed from the iron so that we have access to paint. Please leave side gate unlocked and secure pets indoors. Feel free to call our office with any questions.


Week of 9/29/25: This week we will continue painting view fencing in Parcel 8 in the areas marked in RED. Please make sure that vegetation, decor, lights and critter fencing is removed from the iron so that we have access to paint. Please leave side gate unlocked and secure pets indoors. Feel free to call our office with any questions.

Week of 9/22/25: This week we will continue painting view fencing in Parcel 8 in the areas marked in RED. Please make sure that vegetation, decor, lights and critter fencing is removed from the iron so that we have access to paint. Please leave side gate unlocked and secure pets indoors. Feel free to call our office with any questions.

Week of 9/15/25: This week we will continue painting view fencing in Parcel 8 in the areas marked in BLUE. We will also be prepping and painting the walls in the areas marked in RED. Please make sure that vegetation, decor, lights and critter fencing is removed from the iron so that we have access to paint. Please leave side gate unlocked and secure pets indoors. Feel free to call our office with any questions.

Week of 9/8/25: This week we will continue painting view fencing in Parcel 8 in the areas marked in RED. Please make sure that vegetation, decor, lights and critter fencing is removed from the iron so that we have access to paint. Please leave side gate unlocked and secure pets indoors. Feel free to call our office with any questions.

Week of 9/2/25: This week we will be prepping and painting walls and painting view fencing in Parcel 8 in the areas marked in RED. Please make sure that vegetation, decor, lights and critter fencing is removed from the iron so that we have access to paint. Please leave side gate unlocked and secure pets indoors. Please note that our office will be closed on Monday, 9/1/25 for the Labor Day holiday. Feel free to call our office with any questions.

Week of 8/25/25: This week we will continue painting view fencing in Parcel 8 in the areas marked in RED. Please make sure that vegetation, decor, lights and critter fencing is removed from the iron so that we have access to paint. Please leave side gate unlocked and secure pets indoors. Feel free to call our office with any questions.

Week of 8/18/25: This week we will be painting view fencing in Parcel 8 in the areas marked in RED. Please make sure that vegetation, decor, lights and critter fencing is removed from the iron so that we have access to paint. Please leave side gate unlocked and secure pets indoors. Feel free to call our office with any questions.

Week of 8/11/25: This week, we will be prepping and painting the walls in Parcel 8 in the areas in RED. Please feel free to call our office with any questions.

Week of 8/4/25: This week we will be prepping and painting walls and painting view fencing in Parcel 9 in the areas marked in RED. Please make sure that vegetation, decor, lights and critter fencing is removed from the iron so that we have access to paint. Please leave side gate unlocked and secure pets indoors. Feel free to call our office with any questions.

Week of 7/28/25: This week we will be painting view fencing in Parcel 9 in the areas marked in RED. Please make sure that vegetation, decor, lights and critter fencing is removed from the iron so that we have access to paint. Please leave side gate unlocked and secure pets indoors. Feel free to call our office with any questions.

Week of 7/21/25: This week we will be painting view fencing in Parcel 12 in the areas marked in RED. Please make sure that vegetation, decor, lights and critter fencing is removed from the iron so that we have access to paint. Please leave side gate unlocked and secure pets indoors. We will also start prepping and painting the walls in Parcel 9 in the areas marked in PURPLE. Feel free to call our office with any questions.


Week of 7/14/25: This week we will be painting view fencing in the areas marked in RED. Please make sure that vegetation, decor, lights and critter fencing is removed from the iron so that we have access to paint. Please leave side gate unlocked and secure pets indoors. Feel free to call our office with any questions.

Week of 7/7/25: We are excited to start the painting project in Eagle Mountain Phase 1. This week, we will be prepping and painting the walls in the areas in RED. Please feel free to call our office with any questions.