Hello Residents!

Week of 7/6/26: This week, we will be painting the wall trim in Section 2 in the areas marked in RED. We will also start painting the body of the walls in Section 2 in the areas marked in BLUE.  Feel free to call our office with any questions.

Week of 6/29/26: This week, we will continue prepping and painting Section 2 in the areas marked in BLUE.  Our office will be closed on Friday, 7/3 for the July 4th Holiday.  The crew will be back onsite on Monday, 7/6.  Feel free to call our office with any questions.

 

Week of 6/22/26: This week, we will start prepping and painting Section 2 (BLUE).  Feel free to call our office with any questions.

Week of 6/15/26: This week, we will continue painting the areas in Section 1 marked in RED.  We will also power wash the walls in Section 2 marked in BLUE.  Feel free to call our office with any questions.

Week of 6/8/26: Last week, we completed prepping and painting the areas marked in RED. This week, we will continue prepping and painting the areas in Section 1 marked in BLUE.  Feel free to call our office with any questions.