The Villas at Camelback Crossing

Hello Residents For the week of 9/3: We’ll be closed on Monday for Labor Day. On Tuesday our crew will complete Building 18. Miscellaneous painting in the community will follow. Please contact our office with questions. For the week of 8/27: Painting will begin on Building 18 on Monday (it was power washed and prepped last Friday) […]

Rancho El Mirage

Hello Residents For the week of 10/9: Our crew will be onsite finishing up all touch-ups by Wednesday to complete all work in the community. For the week of 9/25: Our crew will be finishing trim painting and prep work on common walls in Section 6 on Monday/Tuesday. The main body color painting of Section […]

Overlook II

Hello Residents For the week of 11/20: Our crew will be finishing iron gates on Monday, and doing any necessary touch-up work on Tuesday and Wednesday. The pool fencing is also expected to be completed on Wednesday. **This will wrap up all of the general community painting.** Be advised that door staining will continue after […]

Sarival

Hello Residents For the week of 9/11: Our wall crew has completed painting the common area walls throughout the community. Our iron crew is onsite painting throughout the same sections. Homes that have iron view fencing to be painted will receive notice for yard access 3 days in advance. Please keep your gate unlocked, pets inside, […]

Pinnacle Peak Reserve

Hello Residents For the week of 6/19: Our crew will be painting rod iron view fencing for Lots 37-55 in PR1 South (along 72nd Place & Desert Vista Rd) and also Lots 55-61 & 62-71 in PR1 North (along Happy Valley Rd & 74th Place). Please make sure that all vegetation, chicken wire, decor, etc […]

Tatum Highlands

Hello Residents Iron painting has been completed as of 10/20. If your iron view fencing was unable to be painted, please call our office as soon as possible. For the week of 10/16: Our iron crew will continue with the painting in Section 22 (yellow) and complete it this week (approx Thursday). Section 20 (green) […]

Castle Chase HOA

Job has been completed. Hello Residents For the week of 7/10: Our crew is back on-site painting the pool clubhouse and doing any needed touch-ups on the iron view fencing throughout the community. For the week of 6/26: Our wall crew has completed all common area walls. Our iron crew is painting the remaining iron […]

Glen Eagle

Hello Residents For the week of 5/30: Our crew has completed iron view fence painting for lots 65-56 and 55-48 as of Tuesday. All painting (except community light poles) is complete (walls and iron). Please call or email with questions. For the week of 5/22: Our crew will be finishing the iron painting for lots […]

Quail Run

Hello Residents For the week of 5/8: Building K has been completed. The clubhouse painting will be finished on Monday and this will complete the painting of Quail Run. For the week of 5/1: Our crew is expected to be finished with Building K by Tuesday. They will begin on the community clubhouse on Wednesday […]

Arioso City Lofts

Hello Residents For the week of 8/21: Our crew has finished all buildings in the community. Remaining touch-ups are expected to be completed on Tuesday. The remaining missed doors are to be scheduled for Saturday. Feel free to call or email with questions. For the week of 8/14: Our crew is painting the leasing office/fitness […]

T1 Weekly Progress Reports

Hello Residents For the week of 10/16: All community painting has been completed. Our crew will be notifying homeowners that still need some touch-ups done.  For the week of 10/9: Our crew will be painting Lots 503-506 & 507-509 (5215-5209 & 5207-5203) on Half Moon Dr this week. All homes are expected to be completed […]

Mountain Bridge 2017

Hello Residents For the week of 3/6/2017 our crew will be painting iron from lots 37-46 & 47-56 in Carmel. This will complete iron painting in this section. Please make sure that the iron view fencing is cleared for painting & that all pets are kept inside. Feel free to call or email with any […]

Roseview Weekly Progress

Hello Residents For the week of 2/13/17: our crew is painting the iron on the west side of 133rd Ave from Greenway to Waddell. This is the final section of painting to complete our work in Roseview. Feel free to contact our office with any questions. For the week of 2/6/2017: Our crew is working […]

Pueblo Anderson Springs

*Painting has been completed as of 12/9/2016* Hello Residents, For the week of 12/5/2016 our crew is painting Buildings 48 & 55. 48 is expected to be completed by Tuesday, and 55 by Friday. Dates and times are subject to change. Please call our office with any  questions.   For the week of 11/28/2016 our crew is painting […]

Barolo Place condominiums

Hello Residents, For the week of 2/27/2017: Building 7 is completed. The pool and perimeter iron is being painted and should be finished mid week, weather permitting. This will complete our work in the community. If you have a door that hasn’t been able to be painted, please contact our office asap. For the week […]