Town Center Crossing 2026

Town Center Crossing 2026

Hello Residents,

Week of 11/30/26: This week, we will be power wash, prep and paint Building G and Building H marked in RED.  Power washing will be done on Monday, 11/30.  Please make sure that vegetation, decor, lights and critter fencing are removed from the walls and iron so that we have access to paint.  All patio items, including furniture/rugs/grills/wall decorations/TVs/other items attached to the building should be moved to the center of the patio and covered, moved inside, or moved to the garage.  Furniture will not be covered during power washing, so if it is not covered on Monday, 11/30, it will get wet.  We will cover furniture during painting.  Feel free to call our office with any questions.

Week of 11/23/26: This week, we will be repainting the stucco at Buildings C and D marked in RED, due to a change in the paint product being used on the buildings.  Please make sure that vegetation, decor, lights and critter fencing are removed from the walls and iron so that we have access to paint.  All patio items, including furniture/rugs/grills/wall decorations/TVs/other items attached to the building should be moved to the center of the patio and covered, moved inside, or moved to the garage.   Feel free to call our office with any questions.

Week of 11/16/26: This week, we will be repainting the stucco at Buildings E and F marked in RED, due to a change in the paint product being used on the buildings.  We will paint front doors and garage doors on Friday, 11/20.    Please make sure that vegetation, decor, lights and critter fencing are removed from the walls and iron so that we have access to paint.  All patio items, including furniture/rugs/grills/wall decorations/TVs/other items attached to the building should be moved to the center of the patio and covered, moved inside, or moved to the garage.   Feel free to call our office with any questions.

Week of 11/9/26: This week, we will continue painting Building C and D marked in  RED.  We will paint front doors and garage doors on Tuesday, 11/10.  We will also power wash and start to prep and paint Building E and F marked in BLUE on Tuesday, 11/10.  Please make sure that vegetation, decor, lights and critter fencing are removed from the walls and iron so that we have access to paint.  All patio items, including furniture/rugs/grills/wall decorations/TVs/other items attached to the building should be moved to the center of the patio and covered, moved inside, or moved to the garage.   Feel free to call our office with any questions.

Week of 11/2/26: This week, we will continue painting Building A and B marked in  BLUE.  We will paint front doors and garage doors on Tuesday, 11/3.  We will also power wash and start to prep and paint Building C and D on Tuesday, 11/3.  Please make sure that vegetation, decor, lights and critter fencing are removed from the walls and iron so that we have access to paint.  All patio items, including furniture/rugs/grills/wall decorations/TVs/other items attached to the building should be moved to the center of the patio and covered, moved inside, or moved to the garage.   Feel free to call our office with any questions.

Week of 10/26: We are excited to start the painting project in Town Center Crossing this week.  On Wednesday,10/28, we will start to prep and paint Building A and B marked in RED on the attached map. Please make sure that vegetation, decor, lights and critter fencing are removed from the walls and iron so that we have access to paint.  All patio items, including furniture/rugs/grills/wall decorations/TVs/other items attached to the building should be moved to the center of the patio and covered, moved inside, or moved to the garage.   Feel free to call our office with any questions.