Entrada at Mountain Bridge 2026

Entrada at Mountain Bridge 2026

Hello Residents!

Week of 6/1/26: This week, we will be prepping and painting Lot 76-Lot 80 (RED).  We will also continue completing additional painting requested (BLUE).  Please make sure that vegetation, decor, lights and critter fencing are removed from the walls and iron so that we have access to paint.  All condo patio items, including furniture/rugs/grills/wall decorations/TVs/other items attached to the building are moved to the center of the patio and covered, moved inside, or moved to the garage.  Feel free to call our office with any questions.

Week of 5/26/26: This week, we will be prepping and painting Lot 71-Lot 75 (RED).  We will also be completing additional painting requested on Wednesday, 5/27 and Thursday, 5/28 (BLUE).  Please make sure that vegetation, decor, lights and critter fencing are removed from the walls and iron so that we have access to paint.  All condo patio items, including furniture/rugs/grills/wall decorations/TVs/other items attached to the building are moved to the center of the patio and covered, moved inside, or moved to the garage.   Our office will be closed for Memorial Day on Monday, 5/25 and the crew will be back on site Tuesday, 5/26.  Feel free to call our office with any questions.

Week of 5/18/26: Next week, we will be prepping and painting Lot 66-Lot 70 (RED).  Please make sure that vegetation, decor, lights and critter fencing are removed from the walls and iron so that we have access to paint.  All condo patio items, including furniture/rugs/grills/wall decorations/TVs/other items attached to the building are moved to the center of the patio and covered, moved inside, or moved to the garage.   Feel free to call our office with any questions.

Week of 5/11/26: Next week, we will be prepping and painting Lot 61-Lot 65 (RED).  Please make sure that vegetation, decor, lights and critter fencing are removed from the walls and iron so that we have access to paint.  All condo patio items, including furniture/rugs/grills/wall decorations/TVs/other items attached to the building are moved to the center of the patio and covered, moved inside, or moved to the garage.   Feel free to call our office with any questions.

Week of 5/4/26: Next week, we will be prepping and painting Lot 56-Lot 60 (RED).  Please make sure that vegetation, decor, lights and critter fencing are removed from the walls and iron so that we have access to paint.  All condo patio items, including furniture/rugs/grills/wall decorations/TVs/other items attached to the building are moved to the center of the patio and covered, moved inside, or moved to the garage.   Feel free to call our office with any questions.

Week of 4/27/26: Next week, we will be prepping and painting Lot 51-Lot 55 (RED).  Please make sure that vegetation, decor, lights and critter fencing are removed from the walls and iron so that we have access to paint.  All condo patio items, including furniture/rugs/grills/wall decorations/TVs/other items attached to the building are moved to the center of the patio and covered, moved inside, or moved to the garage.   Feel free to call our office with any questions.

Week of 4/20/26: Next week, we will be prepping and painting Lot 46-Lot 50 (RED).  Please make sure that vegetation, decor, lights and critter fencing are removed from the walls and iron so that we have access to paint.  All condo patio items, including furniture/rugs/grills/wall decorations/TVs/other items attached to the building are moved to the center of the patio and covered, moved inside, or moved to the garage.   Feel free to call our office with any questions.

Week of 4/13/26: Next week, we will be completing additional painting requested at Lot 36 – Lot 40 (BLUE).  We will also be prepping and painting Lot 41 – Lot 45 (RED).  Please make sure that vegetation, decor, lights and critter fencing are removed from the walls and iron so that we have access to paint.  All condo patio items, including furniture/rugs/grills/wall decorations/TVs/other items attached to the building are moved to the center of the patio and covered, moved inside, or moved to the garage.   Feel free to call our office with any questions.

Week of 4/6/26: Next week, we will be completing additional painting requested at Lot 31 – Lot 35 (BLUE).  We will also be prepping and painting Lot 36 – Lot 40 (RED).  Please make sure that vegetation, decor, lights and critter fencing are removed from the walls and iron so that we have access to paint.  All condo patio items, including furniture/rugs/grills/wall decorations/TVs/other items attached to the building are moved to the center of the patio and covered, moved inside, or moved to the garage.   Feel free to call our office with any questions.

Week of 3/30/26: Next week, we will be prepping and painting Lot 31 – Lot 35 (RED).  Please make sure that vegetation, decor, lights and critter fencing are removed from the walls and iron so that we have access to paint.  All condo patio items, including furniture/rugs/grills/wall decorations/TVs/other items attached to the building are moved to the center of the patio and covered, moved inside, or moved to the garage.   Feel free to call our office with any questions.

Week of 3/23/26: Next week, we will be prepping and painting Lot 26 – Lot 30 (RED).  On Monday, 3/23 we will be completing additional painting requested at Lot 21 and Lot 25 (BLUE).   Please make sure that vegetation, decor, lights and critter fencing are removed from the walls and iron so that we have access to paint.  All condo patio items, including furniture/rugs/grills/wall decorations/TVs/other items attached to the building are moved to the center of the patio and covered, moved inside, or moved to the garage.   Feel free to call our office with any questions.

Week of 3/16/26: Next week, we will be prepping and painting Lot 21 – Lot 25 (RED).  On Monday, 3/16 we will also be painting courtyard gates that have not been completed at Lot 11-Lot 20 (BLUE).   Please make sure that vegetation, decor, lights and critter fencing are removed from the walls and iron so that we have access to paint.  All condo patio items, including furniture/rugs/grills/wall decorations/TVs/other items attached to the building are moved to the center of the patio and covered, moved inside, or moved to the garage.   Feel free to call our office with any questions.

Week of 3/9/26:  This week, we will be painting Lot 16 – Lot 20 (RED). Please make sure that vegetation, decor, lights and critter fencing are removed from the walls and iron so that we have access to paint.  All condo patio items, including furniture/rugs/grills/wall decorations/TVs/other items attached to the building are moved to the center of the patio and covered, moved inside, or moved to the garage.   Feel free to call our office with any questions.

Week of 3/2/26:  This week, we will be painting Lot 11 – Lot 15 (RED). Please make sure that vegetation, decor, lights and critter fencing are removed from the walls and iron so that we have access to paint.  All condo patio items, including furniture/rugs/grills/wall decorations/TVs/other items attached to the building are moved to the center of the patio and covered, moved inside, or moved to the garage.   Feel free to call our office with any questions.

 

Week of 2/23/26:  This week, we will finish painting Lot 1 – Lot 5 (BLUE).  We will also be prepping and painting Lot 6 – Lot 10 (RED).  Please make sure that vegetation, decor, lights and critter fencing are removed from the walls and iron so that we have access to paint.  All condo patio items, including furniture/rugs/grills/wall decorations/TVs/other items attached to the building are moved to the center of the patio and covered, moved inside, or moved to the garage.   Feel free to call our office with any questions.

Week of 2/16/26: We are excited to be starting the painting project at Entrada at Mountain Bridge this week!  This week, we will be prepping and painting Lot 1 – Lot 5 (RED).  Please make sure that vegetation, decor, lights and critter fencing are removed from the walls and iron so that we have access to paint.  All condo patio items, including furniture/rugs/grills/wall decorations/TVs/other items attached to the building are moved to the center of the patio and covered, moved inside, or moved to the garage.   Feel free to call our office with any questions.

 