Hello Residents
Job has been completed, except for some doors that were unable to be painted due to access issues. Our crew will be back out but date is TBD. Remaining homeowners will be notified when we have further information. Stay tuned!
Happy New Year! For the week of 1/2/2017 our crew is onsite painting carports, doors, & doing some touch-ups. Feel free to call with questions.
For the week of 12/19/2016: our crew is continuing the painting of Building C which is expected to be completed on Friday and that will wrap up the whole job.
For the week of 12/12/2016 our crew is continuing the painting of Building C which should be completed mid-week. (Building G has also been completed which wasn’t indicated on previous updates). Please make sure patios are cleared for painting. Dates and times are subject to change. Please call our office with any questions.
For the week of 12/5/2016 our crew is painting Building C. It’s expected to take 7 working days. Dates and times are subject to change. Please call our office with any questions.
For the week of 11/28/2016 our crew is painting Building M. Rain days & Thanksgiving have delayed progress but painting will continue on Tuesday through the end of the week.
For the week of 11/21/2016 *Painting has been delayed due to rain. Painting for Building M will continue this week*
For the week of 11/14/2016 our crew is finishing the painting of Building F. Building M will be started on Wednesday and is expected to take approximately 1 full week to complete. Please make sure that the patio area is cleared for painting. See the attached map to view which buildings have been painted up to this point (all completed buildings have been highlighted for reference). Dates and times are subject to change. Please contact our office with any questions at 602-795-0696 or email [email protected].
For the week of 11/7/2016 our crew is onsite prepping and painting Building F. Building F is expected to take approximately 1 full week to complete. Please see the attached map to view which buildings have been painted up to this point (all completed buildings have been highlighted for reference). Dates and times are subject to change. Please contact our office with any questions at 602-795-0696 or email [email protected].
Hello residents 🙂
HAPPY HALLOWEEN! For the week of 10/31/2016 our crew is onsite finishing Building H. Building H will be completed on Monday. Power washing for Building L will start Monday and painting will begin on Tuesday. Building L is expected to take approximately 1 full week to complete. Please see the attached map to view which buildings have been painted up to this point (all completed buildings have been highlighted for reference). Dates and times are subject to change. Please contact our office with any questions at 602-795-0696 or email [email protected].
Hello residents 🙂
For the week of 10/24/2016 our crew is onsite painting Building H. Building H is expected to take approximately 1 full week to complete. Residents in Building L will soon be notified for prep work to begin on 10/31. Please see the attached map to view which buildings have been painted up to this point (all completed buildings have been highlighted for reference). Dates and times are subject to change. Please contact our office with any questions at 602-795-0696 or email [email protected].