Tesoro at Grayhawk

Hello Residents

ATTN: Painting is completed in Tesoro. If you have door edges that were unable to be painted previously, our crew will only be returning 5/26 & 6/2 to paint them. Please contact our office.

For the week of 4/30: All buildings that were scheduled to be painted have been completed. We have a crew onsite this week painting electrical boxes and completing touch ups. Feel free to contact our office if you have any questions. 

For the week of 4/23: Building 39 will be completed on Monday. Building 40 will be power washed on Tuesday followed by prepping and painting. B40 is expected to be completed the following Monday. Please remove any exterior decor and place any furniture in the middle of your 1st floor patio. If you have 2nd floor balconies – remove all furniture, as the balcony floors will be re-coated. As a precaution – either park your vehicles in guest parking, away from the painters, or cover the back of your vehicles in the garage.

For the week of 4/16: Painting for Building 38 was slightly delayed due to a couple of days of high winds last week. B38 will be completed on Monday and Building 39 will be started on Tuesday (completed the following Monday, weather permitting). Please remove any exterior decor and place any furniture in the middle of your 1st floor patio. If you have 2nd floor balconies – remove all furniture, as the balcony floors will be re-coated. As a precaution – either park your vehicles in guest parking, away from the painters, or cover the back of your vehicles in the garage.

For the week of 4/9: Our crew will be power washing and prepping Building 38 on Monday. Painting will begin on Tuesday and throughout the week. Please remove any exterior decor and place any furniture in the middle of your 1st floor patio. If you have 2nd floor balconies – remove all furniture, as the balcony floors will be re-coated. As a precaution – either park your vehicles in guest parking, away from the painters, or cover the back of your vehicles in the garage.

For the week of 4/2: Our crew will be power washing and prepping Building 37 on Monday. Painting will begin on Tuesday and throughout the week. Please remove any exterior decor and place any furniture in the middle of your 1st floor patio. If you have 2nd floor balconies – remove all furniture, as the balcony floors will be re-coated. As a precaution – either park your vehicles in guest parking, away from the painters, or cover the back of your vehicles in the garage.

For the week of 3/26: Our crew will be power washing and prepping Building 36 on Monday. Painting will begin on Tuesday and throughout the week. Please remove any exterior decor and place any furniture in the middle of your 1st floor patio. If you have 2nd floor balconies – remove all furniture, as the balcony floors will be re-coated. As a precaution – either park your vehicles in guest parking, away from the painters, or cover the back of your vehicles in the garage.

For the week of 3/19: Our crew will be power washing and prepping Building 35 on Monday. Painting will begin on Tuesday and throughout the week. Please remove any exterior decor and place any furniture in the middle of your 1st floor patio. If you have 2nd floor balconies – remove all furniture, as the balcony floors will be re-coated. As a precaution – either park your vehicles in guest parking, away from the painters, or cover the back of your vehicles in the garage.

For the week of 3/12: Our crew will be power washing and prepping Building 34 on Monday. Painting will begin on Tuesday and throughout the week. Please remove any exterior decor and place any furniture in the middle of your 1st floor patio. If you have 2nd floor balconies – remove all furniture, as the balcony floors will be re-coated. As a precaution – either park your vehicles in guest parking, away from the painters, or cover the back of your vehicles in the garage.

For the week of 3/5: (Building 32 will be completed on Monday or Tuesday). Our crew is power washing Building 33 on Monday and proceeding with prepping and painting through the week. B33 is expected to be completed on Friday. Please remove any exterior decor and place any furniture in the middle of your 1st floor patio. If you have 2nd floor balconies – remove all furniture, as the balcony floors will be re-coated. As a precaution – either park your vehicles in guest parking, away from the painters, or cover the back of your vehicles in the garage.

For the week of 2/26: Our crew is painting Building 32 and expect to have it completed on Thursday. Power Washing for Building 33 is expected to begin on Friday and (B33) completed the following Thursday (weather permitting). Please remove any exterior decor and place any furniture in the middle of your 1st floor patio. If you have 2nd floor balconies – remove all furniture, as the balcony floors will be re-coated. As a precaution – either park your vehicles in guest parking, away from the painters, or cover the back of your vehicles in the garage. 

For the week of 2/19: *Rain delay last week* Our crew is expected to complete Building 31 on Thursday, and start Building 32 (power washing) on Friday. Please remove any exterior decor and place any furniture in the middle of your 1st floor patio. If you have 2nd floor balconies – remove all furniture, as the balcony floors will be re-coated. As a precaution – either park your vehicles in guest parking, away from the painters, or cover the back of your vehicles in the garage. 

For the week of 2/12: Our crew will be completing Building 30 on Tuesday and starting Building 31 (power washing) on Wednesday. Building 31 is expected to be completed on 2/20, weather permitting. Please remove any exterior decor and place any furniture in the middle of your 1st floor patio. If you have 2nd floor balconies – remove all furniture, as the balcony floors will be re-coated. As a precaution – either park your vehicles in guest parking, away from the painters, or cover the back of your vehicles in the garage. 

For the week of 2/5: Our crew will be completing Building 29 on Tuesday and starting Building 30 (power washing) on Wednesday. B30 is expected to be completed on 2/13. Please remove any exterior decor and place any furniture in the middle of your 1st floor patio. If you have 2nd floor balconies – remove all furniture, as the balcony floors will be re-coated. As a precaution – either park your vehicles in guest parking, away from the painters, or cover the back of your vehicles in the garage. 

For the week of 1/29: Our crew will be completing Building 28 on Tuesday and starting Building 29 on Wednesday. B29 is expected to be completed on 2/6. Please remove any exterior decor and place any furniture in the middle of your 1st floor patio. If you have 2nd floor balconies – remove all furniture, as the balcony floors will be re-coated. As a precaution – either park your vehicles in guest parking, away from the painters, or cover the back of your vehicles in the garage.

For the week of 1/22: Building 27 will be completed on Tuesday. Building 28 will be power washed, prepped, and painted starting Wednesday and is expected to be completed next Tuesday, 1/30. Please remove any exterior decor and place any furniture in the middle of your 1st floor patio. If you have 2nd floor balconies – remove all furniture, as the balcony floors will be re-coated. As a precaution – either park your vehicles in guest parking, away from the painters, or cover the back of your vehicles in the garage.

For the week of 1/15: Our crew will be completing  Building 26 on Tuesday (the rainstorm last week delayed us 1 day). Building 27 will begin on Wednesday with power washing & prepping. B27 is expected to be completed the following Tuesday. Please remove any exterior decor and place any furniture in the middle of your 1st floor patio. If you have 2nd floor balconies – remove all furniture, as the balcony floors will be re-coated. As a precaution – either park your vehicles in guest parking, away from the painters, or cover the back of your vehicles in the garage.

For the week of 1/8/2018: Our crew will be completing Building 25 on Monday. Power washing, prepping, and painting of Building 26 will begin on Tuesday, and is expected to be completed the following Monday (1/15). Please remove any exterior decor and place any furniture in the middle of your 1st floor patio. If you have 2nd floor balconies – remove all furniture, as the balcony floors will be re-coated. As a precaution – either park your vehicles in guest parking, away from the painters, or cover the back of your vehicles in the garage.

For the week of 1/2/2018: Happy New Year! Our crew will be power washing, prepping, and painting Building 25 starting Tuesday, and expect to have to have it completed on Monday 1/8. Please remove any exterior decor and place any furniture in the middle of your 1st floor patio. If you have 2nd floor balconies – remove all furniture, as the balcony floors will be re-coated. As a precaution – either park your vehicles in guest parking, away from the painters, or cover the back of your vehicles in the garage.

For the week of 12/25: We will be closed from Christmas Day through New Year’s Day. We will reopen on Tuesday, January 2nd, 2018. Happy Holidays! 

For the week of 12/18: Our crew will be painting Building 24 and expect to have it completed by the end of the week. Please remove any exterior decor and place any furniture in the middle of your 1st floor patio. If you have 2nd floor balconies – remove all furniture, as the balcony floors will be re-coated. As a precaution – either park your vehicles in guest parking, away from the painters, or cover the back of your vehicles in the garage. 

For the week of 12/11: Our crew will be painting Building 23 and expect to have it completed by the end of the week. Please remove any exterior decor and place any furniture in the middle of your 1st floor patio. If you have 2nd floor balconies – remove all furniture, as the balcony floors will be re-coated. As a precaution – either park your vehicles in guest parking, away from the painters, or cover the back of your vehicles in the garage.

For the week of 12/4: Our crew will be power washing, prepping, and painting Building 22 and expect to have it completed on Thursday. They’ll begin power washing Building 23 on Friday. Please remove any exterior decor and place any furniture in the middle of your 1st floor patio. If you have 2nd floor balconies – remove all furniture, as the balcony floors will be re-coated. As a precaution – either park your vehicles in guest parking, away from the painters, or cover the back of your vehicles in the garage.

For the week of 11/27: This week our crew will be prepping and painting the community clubhouse. Feel free to call or email our office with any questions.