Hello Residents!
For the week of 5/6/24: We will be finishing in your community with the final Community Center painting and light posts near the game area. Feel free to contact our office with any questions.
We appreciate your business and thank you for using Titan Painting!
For the week of 4/29/24: We will be going back to complete all skipped iron on Monday. IF YOU RECEIVE A NOTICE, PLEASE WORK WITH US TO COMPLETE YOUR FENCING. Please remove chicken wire/critter fencing, vegetation, lights, decor, etc. to allow clear access to paint the iron. Please allow access through your side gate and secure pets indoors. Feel free to contact our office with any questions.
We appreciate your business and thank you for using Titan Painting!
For the week of 4/22/24: We will be going back to complete all skipped iron and iron repairs this week. IF YOU RECEIVE A NOTICE, PLEASE WORK WITH US TO COMPLETE YOUR FENCING. Please remove chicken wire/critter fencing, vegetation, lights, decor, etc. to allow clear access to paint the iron. Please allow access through your side gate and secure pets indoors. Feel free to contact our office with any questions.
For the week of 4/16/24: We will be working in Desert Crown East this week. After that, we will go back to paint all skipped iron. Please remove chicken wire/critter fencing, vegetation, lights, decor, etc. to allow clear access to paint the iron. Please allow access through your side gate and secure pets indoors. Feel free to contact our office with any questions.
For the week of 4/1/24: We will be working in Desert Crown East this week on areas marked in RED. After that, we will be going back to paint all skipped fencing. If you receive a notice, please prepare for us to make the paint process as efficient as possible. Please remove chicken wire/critter fencing, vegetation, lights, decor, etc. to allow clear access to paint the iron. Please allow access through your side gate and secure pets indoors. Feel free to contact our office with any questions.
For the week of 3/25/24: We will be working in Desert Sierra and beginning in Desert Crown West this week in areas marked in BLUE. Please remove chicken wire/critter fencing, vegetation, lights, decor, etc. to allow clear access to paint the iron. Please allow access through your side gate and secure pets indoors. Feel free to contact our office with any questions.
For the week of 3/18/24: We will be working in Desert Sierra this week in areas marked in BLUE. Please remove chicken wire/critter fencing, vegetation, lights, decor, etc. to allow clear access to paint the iron. Please allow access through your side gate and secure pets indoors. Feel free to contact our office with any questions.
For the week of 3/11/24: We will be finishing in Desert Crossing in the RED area. Please remove chicken wire/critter fencing, vegetation, lights, decor, etc. to allow clear access to paint the iron. Please allow access through your side gate and secure pets indoors. Feel free to contact our office with any questions.
For the week of 3/4/24: We will be finishing in Desert Cove in the RED area and then moving on to Desert Crossing in BLUE. Please remove chicken wire/critter fencing, vegetation, lights, decor, etc. to allow clear access to paint the iron. Please allow access through your side gate and secure pets indoors. Feel free to contact our office with any questions.
For the week of 2/26/24: We will be painting iron in the RED areas of the map in Desert Cove this week. Please remove chicken wire/critter fencing, vegetation, lights, decor, etc. to allow clear access to paint the iron. Please allow access through your side gate and secure pets indoors. Feel free to contact our office with any questions.
For the week of 2/19/24: We will be focusing on going back to paint all skipped iron this week. Next week we will begin painting iron in Desert Cove. If you have received a notification from your property manager, please prepare for us. Please remove chicken wire/critter fencing, vegetation, lights, decor, etc. to allow clear access to paint the iron. Please allow access through your side gate and secure pets indoors. Feel free to contact our office with any questions.
For the week of 2/12/24: We have finished painting walls in Desert Cove and will now start the walls in Desert Crossing (RED). Please remove chicken wire/critter fencing, vegetation, lights, decor, etc. to allow clear access to paint the iron. Please allow access through your side gate and secure pets indoors. Feel free to contact our office with any questions.
For the week of 1/29/24: Our crew will be painting the entry gate at Desert Crest and any fencing marked in BLUE. Then we will move on to Desert Cove. Please remove chicken wire/critter fencing, vegetation, lights, decor, etc. to allow clear access to paint the iron. Please allow access through your side gate and secure pets indoors. Feel free to contact our office with any questions.
For the week of 1/22/24: Our crew will be painting the entry gate at Desert Crest along with all fencing marked in GREEN. Then we will begin to prep in Desert Crossing. Please remove chicken wire/critter fencing, vegetation, lights, decor, etc. to allow clear access to paint the iron. Please allow access through your side gate and secure pets indoors. Feel free to contact our office with any questions.
For the week of 1/15/24: Our crew will begin going back to paint all skipped iron this week and next. We will begin in Desert Enclave, Desert Vistas and Desert Point. After that we will move on to Desert Springs, Desert Pass North, and Desert Trails North. Please remove chicken wire/critter fencing, vegetation, lights, decor, etc. to allow clear access to paint the iron. Please allow access through your side gate and secure pets indoors. Feel free to contact our office with any questions.
For the week of 1/8/24: Our crew will be working on iron marked in GREEN in the Desert Crest area. Please remove chicken wire/critter fencing, vegetation, lights, decor, etc. to allow clear access to paint the iron. Please allow access through your side gate and secure pets indoors. Feel free to contact our office with any questions.
For the week of 1/2/24: Happy New Year! Our crew will be working on iron marked in RED in the Desert Crest area. Please remove chicken wire/critter fencing, vegetation, lights, decor, etc. to allow clear access to paint the iron. Please allow access through your side gate and secure pets indoors. Feel free to contact our office with any questions.
For the week of 12/18/23: Our crew will be working on iron marked in RED in the Desert Crest area. Please remove chicken wire/critter fencing, vegetation, lights, decor, etc. to allow clear access to paint the iron. Please allow access through your side gate and secure pets indoors. PLEASE NOTE: we will be closed from 12/21-1/1/24. We wish you a wonderful holiday season! Feel free to contact our office with any questions.
For the week of 12/11/23: Our crew will be finishing all walls marked BLUE. Areas marked in GREEN are iron that we will be focusing on this week. Please remove chicken wire/critter fencing, vegetation, lights, decor, etc. to allow clear access to paint the iron. Please allow access through your side gate and secure pets indoors. Feel free to contact our office with any questions.
For the week of 12/4/23: Blue areas in Desert Crest will be painted this week. Please remove chicken wire/critter fencing, vegetation, lights, decor, etc. to allow clear access to paint the iron. Please allow access through your side gate and secure pets indoors. Feel free to contact our office with any questions.
For the week of 11/27/23: Blue areas will be painted this week and then we will prep and paint walls in the next section of Desert Crest. Please remove chicken wire/critter fencing, vegetation, lights, decor, etc. to allow clear access to paint the iron. Please allow access through your side gate and secure pets indoors. Feel free to contact our office with any questions.
For the week of 11/20/23: Common area wrought iron and entry gates in Desert Canyon (1st map) will be painted followed by prepping common walls in Desert Crest (2nd map). We’ll be closed Thursday and Friday in observance of Thanksgiving. Feel free to contact our office with any questions.
For the week of 11/13/23: Wrought iron view fences marked in yellow will be painted in Desert Canyon. Please remove chicken wire/critter fencing, vegetation, lights, decor, etc. to allow clear access to paint the iron. Please allow access through your side gate and secure pets indoors. Feel free to contact our office with any questions.
For the week 11/6/23: Common area walls (in yellow) in Desert Canyon will be power washed, prepped, and painted this week. Please contact our office with any questions.
For the week of 10/30/23: Common area walls (in red) in Desert Canyon will be power washed, prepped, and painted this week. Please contact our office with any questions.
For the week of 10/23/23: Wrought iron view fences will be painted in Desert Pass South and Desert Trails South this week. Please remove chicken wire/critter fencing, vegetation, lights, decor, etc. to allow clear access to paint the iron. Please allow access through your side gate and secure pets indoors. Feel free to contact our office with any questions.
For the week of 10/16/23: Common area walls marked in blue in Desert Pass South will be power washed, prepped, and painted this week. If you have any questions, please contact our office. Edit to add: *Common area walls were also able to be painted in Desert Trails South.
For the week of 10/9/23: Wrought iron view fences marked in red in Desert Pass North will be painted starting on Monday. Please remove chicken wire/critter fencing, vegetation, lights, decor, etc. to allow clear access to paint the iron. Please allow access through your side gate and secure pets indoors. Common area walls in Desert Pass will start being prepped following the iron in DPN. Feel free to contact our office with any questions.
For the week of 10/2/23: Wrought iron view fences marked in yellow in Desert Trails North will be painted this week. Please remove chicken wire/critter fencing, vegetation, lights, decor, etc. to allow clear access to paint the iron. Please allow access through your side gate and secure pets indoors. Feel free to contact our office with any questions.
For the week of 9/25/23: Entrance gates will continue being painted for Desert Springs and Desert Trails North. Common area walls in Desert Pass North will start to be prepped on Wednesday. Please contact our office with any questions.
For the week of 9/18/23: Entrance gates will be painted in Desert Vistas, Desert Point, Desert Springs, and Desert Trails North. Please contact our office with any questions.
For the week of 9/11/23: Common area walls marked in red in Desert Trails North will be prepped and painted this week (walls in yellow are done). If you have any questions, please contact our office.
For the week of 9/4/23: We’re closed Monday for Labor Day. Starting on Tuesday, common area walls in Desert Trails North (marked in yellow) will be prepped and painted. Contact our office with any questions.
For the week of 8/28/23: Wrought iron view fences marked in red in Desert Springs will be painted throughout the week. Please remove chicken wire/critter fencing, vegetation, lights, decor, etc. to allow clear access to paint the iron. Please allow access through your side gate and secure pets indoors. Feel free to contact our office with any questions.
For the week of 8/21/23: Common area walls marked in blue in Desert Springs will be prepped and painted throughout the week (common walls in red area done). Feel free to contact our office with any questions.
For the week of 8/14/23: Common area walls (red) in Desert Springs will be prepped and painted throughout the week. Wrought iron view fences in Desert Point will be painted Tuesday and Wednesday. Please remove chicken wire/critter fencing, vegetation, lights, decor, etc. to allow clear access to paint the iron. Please allow access through your side gate and secure pets indoors. Feel free to contact our office with any questions.
For the week of 8/7/23: Common area walls in Desert Point will start being prepped and painted (1st and 2nd maps). Wrought iron view fences in Desert Vistas (3rd map) will also be painted. For iron, please remove chicken wire/critter fencing, vegetation, lights, decor, etc. to allow clear access to paint the iron. Please allow access through your side gate and secure pets indoors. Feel free to contact our office with any questions.
For the week of 7/31/23: All areas circled on the maps will be painted this week. Please remove chicken wire/critter fencing, vegetation, lights, decor, etc. to allow clear access to paint the iron. Please allow access through your side gate and secure pets indoors. Feel free to contact our office with any questions.
For the week of 7/24/23: Wrought iron view fences in Enclave will be painted throughout the week. Please remove chicken wire/critter fencing, vegetation, lights, decor, etc. to allow clear access to paint the iron. Please allow access through your side gate and secure pets indoors. Feel free to contact our office with any questions.
We will also be prepping the area indicated in green below:
For the week of 7/17/23: Wrought iron view fences in Enclave will be painted throughout the week. Please remove chicken wire/critter fencing, vegetation, lights, decor, etc. to allow clear access to paint the iron. Please allow access through your side gate and secure pets indoors. Feel free to contact our office with any questions.
For the week of 7/10/23: Common area walls marked in orange in Enclave will be power washed and painted. If you have any questions, please contact our office.
For the week of 7/3/23: We are closed Monday and Tuesday in observance of Independence Day. Starting Wednesday, common area walls in Enclave will be prepped. Please contact our office with any questions.
For the week of 6/26/23: Car entry gates in Desert Crown and Desert Sierra will be painted on Monday. If you have any questions, please contact our office.
For the week of 6/5/23: Wrought iron view fences (marked in blue) will be painted in Desert Sierra. Please remove any vegetation, chicken wire/critter fencing, decor, etc. from the iron so we have clear access to paint the iron. Please allow access through the side gate and secure pets inside. Common area walls marked in red in Desert Sierra and Desert Crown will be painted following the iron. Feel free to contact our office with any questions.
For the week of 5/29/23: Closed Monday in observance of Memorial Day Starting Tuesday, wrought iron view fences (marked in blue) will be painted in Desert Crown (William Lyons). Please remove any vegetation, chicken wire/critter fencing, decor, etc. from the iron so we have clear access to paint the iron. Please allow access through the side gate and secure pets inside. Painting of the pool fencing will follow. Feel free to contact our office with any questions.
For the week of 5/22/23: The Sonoran Foothills pool clubhouse will be painted and exterior walls marked in red will start being painted in Desert Crown (William Lyons). Please contact our office with any questions.
For the week of 5/15/23: Culvert rails will be painted in Desert Crossing. Please contact our office with any questions or concerns.
For the week of 5/1/23: Culvert rails will be painted in Desert Cove. Please contact our office if you have any questions.
For the week of 4/24/23: Culvert rails will continue being painted in the following subdivisions: Desert Pass South, Desert Trails South, Desert Canyon, Desert Crest, and Desert Crossing. Please contact our office with any questions.
For the week of 4/10/23: Culvert rails will be continue being painted in Desert Trails North then Desert Pass North, Desert Pass South, and Desert Trails South. Please contact our office if you have any questions.
For the week of 4/3/23: Culvert rails will be painted in Desert Trails North. Please contact our office if you have any questions.
For the week of 3/27/23: Culvert rails will be painted in Desert Point. Please contact our office if you have any questions.