Hello Residents
For the week of 10/9: Our crew will be onsite finishing up all touch-ups by Wednesday to complete all work in the community.
For the week of 9/25: Our crew will be finishing trim painting and prep work on common walls in Section 6 on Monday/Tuesday. The main body color painting of Section 6 walls will start Tuesday. Iron in Section 6 is also being painted this week. We are expecting to wrap up all work this week.
For the week of 9/18: Our crew will be completing minor touch-ups on the walls in Section 4 and starting the wall painting of Section 5 on Monday. Section 6 is expected to be started by the end of the week as well. Feel free to call or email with questions.
For the week of 9/11: Our crew will be working to finish the trim of Section 4 on Monday, and will start spraying the main body color on Tuesday. They are expected to have S4 completed by the end of the week. Feel free to call or email with any questions.
For the week of 9/4: CLOSED FOR LABOR DAY. Our crew will be painting the main body color of the common area walls in Section 3 this week. They will begin prepping the walls in Section 4 on Thursday, with trim painting expected to begin on Friday. Feel free to call or email with questions.
For the week of 8/28: Our crew will be completing the common area wall painting in Section 2 on Monday. They will start prepping and painting the trim color on the common area walls in Section 3 on Tuesday (this section is expected to take approx 1.5 weeks). Feel free to call or email with any questions.
For the week of 8/21: Our crew will be painting the walls in Section 2 this week starting with the trim and prepping. The main body color should start to be applied on Thursday and Friday. Feel free to call or email with questions.
For the week of 8/14: The painting of the common area walls in Section 1 is continuing this week. Our crew is finishing up the trim paint on Monday and will then paint the main body color for walls along Santa Fe Ln (by the train tracks). Feel free to call or email with any questions.
For the week of 8/7: Our crew will be painting the main body color of the common area walls in Section 1. This section is expected to be completed by the end of the week. Feel free to call or email with any questions.
For the week of 7/31: For the majority of this week our crew will be painting the split-face block on the common area walls in Section 1. They’ll start painting the main body color of the same walls by the end of the week, time permitting. Feel free to call or email with any questions.