For the week of 5/8: Building K has been completed. The clubhouse painting will be finished on Monday and this will complete the painting of Quail Run.
For the week of 5/1: Our crew is expected to be finished with Building K by Tuesday. They will begin on the community clubhouse on Wednesday through the end of the week. This will complete painting in the community.
For the week of 4/24: Building J is being painted and is expected to be completed by Tuesday. Building K will be started on Wednesday and is expected to be completed on Friday. This will complete painting in Quail Run.
For the week of 4/17: Building H will be completed on Monday. Building I will begin on Tuesday and is expected to be completed by Thursday. The prepping of Building J will start on Friday for painting the following week.
For the week of 4/10: The prepping & painting of Building G will begin on Monday and is expected to be completed by Wednesday. Prepping & painting of Building H is expected to begin on Thursday and be completed the following Monday. Please make sure that all decorations are removed from walls and that any patio furniture is placed in the center of the patio. Feel free to call or email with any questions.
For the week of 4/3: Our crew will be completing Building E by Tuesday, & will begin prepping/painting Building F on Wednesday. Building F is expected to be completed on Friday. Please make sure that all decorations are removed from walls and that any patio furniture is placed in the center of the patio. Call or email with questions.
For the week of 3/27 our crew will be painting Building D (building C will be completed on 3/27) and starting Building E (on Thursday). Please make sure that decorations are removed from the walls and that any patio furniture is placed in the center of the patio. Feel free to call or email with any questions.
For the week of 3/20 our crew will be painting Buildings B & C. Please make sure that decorations are removed from the building and any patio furniture is in the center of your patio. Feel free to call or email our office with any questions. *Rain delay 3/23*
For the week of 3/13/2017: Our crew will be starting the painting in Quail Run with Building A. This should take the entire week, with doors being painted on Friday. (power washing & prepping of Building B will begin 3/17). Please make sure that decorations are removed from the building and any patio furniture is in the center of your patio. Feel free to call or email our office with any questions.