Pueblo at Andersen Springs

Hello Residents

*Job completed*

For the week of 12/4: Our crew will be prepping and painting Building 25 and expect to have to have it completed by Thursday or Friday. They’ll also be painting the front entry and pedestrian gates. This will complete all the work scheduled for painting. Feel free to call or email our office with any questions. 

For the week of 11/27: Our crew will be prepping and painting Building 23 and expect to have it completed on Wednesday. Building 24 will be power washed on Wednesday for prepping and painting to begin Thursday. Please remove any exterior decor and place any patio furniture on the middle of your patio. Feel free to call or email our office with any questions.   

For the week of 11/20: Our crew has already begun Building 1 and will have it completed on Tuesday. They will be off-site for the remainder of the week due to Thanksgiving. Painting will resume next Monday (11/27) on Building 23. Please remove any exterior decor and place any patio furniture on the middle of your patio. Feel free to call or email our office with any questions.

 

For the week of 11/13: Building 47 was able to be painted the week of 11/6. Final touch-ups are being completed on Monday (11/13). Our crew will be prepping and painting Buildings 73 and 75 this week. The painting on 73 will begin on Tuesday, and 75 is expected to be started on Thursday. Please remove any exterior decor and place any patio furniture on the middle of your patio. Feel free to call or email our office with any questions.

For the week of 11/6: Our crew will begin painting in the pool area; to include the pool house, pergola, pool fencing, and gates. If you have any questions, feel free to call or email our office. 