Desert Foothills Office Suites

For the week of 1/15: Our crew is painting carports, light poles, and completing necessary touch ups. All painting is expected to be completed on Wednesday. Feel free to call or email with any questions. 

For the week of 1/2/2018: Happy New Year! Our crew will complete the painting of Building 1 on Wednesday. Building 2 will BEGIN on Wednesday. Please remove any decor and place any furniture in the center of patio or in the suite. Feel free to call our office with questions.

For the week of 12/25: We will be closed from Christmas Day through New Year’s Day. We will reopen on Tuesday, January 2nd, 2018. Happy Holidays! 

For the week of 12/18: Our crew will be completing the painting of Building 3 on Monday, and will also be prepping Building 1. Painting for B1 will begin on Tuesday. Please make sure that any exterior decor is removed and any furniture is placed in the center of the patio or in the suite. Feel free to email or call our office with any questions. 

For the week of 12/11: Our crew will begin with the painting of Building 3 and expect to have it completed by the end of the week. Please make sure that any exterior decor is removed and any furniture is placed in the center of your patio or in your suite. Feel free to email or call our office with any questions.