Ahwatukee Foothills Weekly Update

Job has been completed as of 11/23 (all iron repairs included).

For the week of 11/14/2016 our crew is completing iron painting in the communityAll painting will be completed by end of day on Monday EXCEPT for the houses that have notified of iron repairs. Iron repairs will start on Thursday. Please make sure that all pets are kept inside and any vegetation, chicken wire, or other obstructions are removed to allow clear access for painting to be completed. Note that dates are subject to change. Feel free to contact the office with any questions at 602-795-0696 or [email protected].

 

For the week of 11/7/2016 our crew is onsite painting iron view fencing for homes along E Briarwood Ter. Completion of all community painting is expected to be done by Wednesday 11/9. Please make sure that all pets are kept inside and any vegetation, chicken wire, or other obstructions are removed to allow clear access for painting to be completed. Note that dates are subject to change. Feel free to contact the office with any questions at 602-795-0696 or [email protected].

ahwftls

 

Hello residents 🙂

HAPPY HALLOWEEN! For the week of 10/31/2016 our crew is onsite finishing the iron view fence painting behind houses on E Glenhaven Dr. They’ll then be painting common area walls along E Liberty Ln from S 20th Way to E Briarwood Ter. Iron view fence painting for houses along E Briarwood Ter is expected to begin Friday. Note that dates are subject to change. Please make sure that all pets are kept inside and any vegetation, chicken wire, or other obstructions are removed to allow clear access for painting to be completed. Feel free to contact the office with any questions at 602-795-0696 or [email protected].

libertyln20thway

 

 

 

 

Hello residents 🙂

For the week of 10/24/2016 our crew is onsite painting walls along E Liberty Lane and will continue around to the walls behind houses on S 20th Place. Homes on S 20th Place and E Glenhaven Drive will be receiving notices for iron view fence painting to begin on Friday 10/28/2016. Please make sure that all pets are kept inside and any vegetation, chicken wire, or other obstructions are removed to allow clear access for painting to be completed. Note that dates are subject to change. Feel free to contact the office with any questions at 602-795-0696 or [email protected].

libertyln20thway