Weekly Progress Reports

March 14, 2018 April No Comments

Fiesta Park Village

Hello Residents Painting is completed. Our crew will return to paint skipped doors and edges. Notices will be left to advise of dates. Feel free to contact our office with any questions. For the week of 7/30: Due to a windy weather delay, our crew will finish Building H Tuesday or Wednesday. Building I will […]

March 14, 2018 April No Comments

Island Palms Apartments

Hello Residents  For the week of 6/25: Our crew will be painting the office and carports this week. Please keep an eye out for notices as to which day(s) to move your vehicle for washing/painting. Feel free to contact our office with any questions. For the week of 6/18: Our crew will be power washing and […]

March 5, 2018 April No Comments

Cooper Ranch

Hello Residents For the week of 3/5: Our crew will be painting rod iron view fencing this week and expected to have it all completed by Wednesday. Common walls in the community were painted on 3/2. Please leave your side gate unlocked and remove any vegetation, chicken wire, decor, etc. from the iron view fencing […]

February 23, 2018 April No Comments

Desert Ridge 2018

Hello Residents For the week of 7/23: Our crew is on site finishing some odds and ends painting and will be completed this week. Please contact our office or FirstService immediately if you’re iron view fencing was unable to be painted.  For the week of 7/16: Our wall crew will be completing the exterior walls […]

February 19, 2018 April No Comments

Rosegarden Townhouses

Hello Residents For the week of 2/19/2018: Our crew will be painting back entry gates throughout the week. Due to Monday’s rain delay, painting may continue into the week of 2/26. Please leave gates unlocked and remove any decor from the gates. Please keep pets inside. Call or email our office with any questions. 

January 29, 2018 April No Comments

Eagle Cove

Hello Residents Painting has been completed. For the week of 2/12: All wall painting throughout the community is expected to be completed on Wednesday 2/14/2018.  For the week of 2/5: Our crew will be working on painting the trim on all the remaining common walls throughout the community. Please contact our office with any questions.  […]

January 22, 2018 April No Comments

The Foothills – Zone 6

Hello Residents For the week of 4/23: Our crew will be completing the iron in Black Rock midweek. No crews will be onsite for painting until further notice. If your iron was skipped in any previous parcel, please contact our office so we can make arrangements for painting.  For the week of 4/16: Our crew […]

December 11, 2017 April No Comments

Desert Foothills Office Suites

For the week of 1/15: Our crew is painting carports, light poles, and completing necessary touch ups. All painting is expected to be completed on Wednesday. Feel free to call or email with any questions.  For the week of 1/2/2018: Happy New Year! Our crew will complete the painting of Building 1 on Wednesday. Building […]

November 27, 2017 April No Comments

Patrick Ranch

Hello Residents For the week of 12/18: Our crew was able to paint all exterior common area walls and most of the adjoining neighbor walls for Section 2 last week (smaller section on map). All painting is expected to be completed on Monday, 12/18. Feel free to call or email our office with any questions. […]

November 27, 2017 April No Comments

Tesoro at Grayhawk

Hello Residents ATTN: Painting is completed in Tesoro. If you have door edges that were unable to be painted previously, our crew will only be returning 5/26 & 6/2 to paint them. Please contact our office. For the week of 4/30: All buildings that were scheduled to be painted have been completed. We have a […]

November 27, 2017 April No Comments

Sunland Springs Village Garden Condos

Hello Residents All painting in the community has been completed.  For the week of 2/19: Our crew will be completing the exterior of Units 85-93 on Wednesday, weather permitting (wind & rain on Monday delayed progress 1 day). Doors will be painted on Thursday. Please leave your front and back security screens unlocked on 2/21 & […]

November 6, 2017 April No Comments

Asante Park

Hello Residents For the week of 1/29: Our crew will be completing walls by Monday or Tuesday (in PINK). Some homeowners were notified of iron painting being done this week. Our iron crew expects to have all added iron completed by Wednesday 1/31. This will complete all painting in the community. For the week of 1/22: […]

November 6, 2017 April No Comments

Pueblo at Andersen Springs

Hello Residents *Job completed* For the week of 12/4: Our crew will be prepping and painting Building 25 and expect to have to have it completed by Thursday or Friday. They’ll also be painting the front entry and pedestrian gates. This will complete all the work scheduled for painting. Feel free to call or email our […]

October 23, 2017 April No Comments

Villas at Desert Camp

Hello Residents  For the week of 11/5/2018:  We are on our last building this week – Building 10!  Please remove all decor or vegetation from your building and place all patio furniture in the center of your patio or indoors.  Feel free to contact our office with any questions.  WE APPRECIATE YOU AND THANK YOU […]

October 9, 2017 April No Comments

Rovey Farms

Hello Residents For the week of 10/30: **Our crew will be completed with all community painting this Tuesday.** For the week of 10/23: Our crew will be prepping and painting walls (highlighted yellow on map below) on the South side of Emil Rovey Pkwy. Feel free to call or email with any questions.   For […]