Hello Residents For the week of 4/23: Our crew will be completing the iron in Black Rock midweek. No crews will be onsite for painting until further notice. If your iron was skipped in any previous parcel, please contact our…
Read moreAuthor Archives: April
Desert Foothills Office Suites
For the week of 1/15: Our crew is painting carports, light poles, and completing necessary touch ups. All painting is expected to be completed on Wednesday. Feel free to call or email with any questions. For the week of 1/2/2018:…
Read morePatrick Ranch
Hello Residents For the week of 12/18: Our crew was able to paint all exterior common area walls and most of the adjoining neighbor walls for Section 2 last week (smaller section on map). All painting is expected to be…
Read moreTesoro at Grayhawk
Hello Residents ATTN: Painting is completed in Tesoro. If you have door edges that were unable to be painted previously, our crew will only be returning 5/26 & 6/2 to paint them. Please contact our office. For the week of…
Read moreSunland Springs Village Garden Condos
Hello Residents All painting in the community has been completed. For the week of 2/19: Our crew will be completing the exterior of Units 85-93 on Wednesday, weather permitting (wind & rain on Monday delayed progress 1 day). Doors will…
Read moreAsante Park
Hello Residents For the week of 1/29: Our crew will be completing walls by Monday or Tuesday (in PINK). Some homeowners were notified of iron painting being done this week. Our iron crew expects to have all added iron completed…
Read morePueblo at Andersen Springs
Hello Residents *Job completed* For the week of 12/4: Our crew will be prepping and painting Building 25 and expect to have to have it completed by Thursday or Friday. They’ll also be painting the front entry and pedestrian gates. This…
Read moreVillas at Desert Camp
Hello Residents For the week of 11/5/2018: We are on our last building this week – Building 10! Please remove all decor or vegetation from your building and place all patio furniture in the center of your patio or indoors….
Read moreRovey Farms
Hello Residents For the week of 10/30: **Our crew will be completed with all community painting this Tuesday.** For the week of 10/23: Our crew will be prepping and painting walls (highlighted yellow on map below) on the South side…
Read moreCactus Gates
Hello Residents For the week of 10/23: *Our crew will be completing all community painting this week.* The wall facing FLW will complete all the wall painting, and iron in the community wash will be completed by the end of…
Read moreSan Marcos Manor
Hello Residents For the week of 10/23: Our iron crew will be (electrostatic) painting the view fencing in backyards. They are expected to be completed by the end of the week. Please watch for a notice and make sure that any…
Read moreKierland Progress Report
Hello Residents For the week of 10/2: Our crew will be painting the common area walls facing 64th St. from Greenway to Acoma Dr. Feel free to call or email with any questions. Painting in the community will be completed…
Read moreThe Villas at Camelback Crossing
Hello Residents For the week of 9/3: We’ll be closed on Monday for Labor Day. On Tuesday our crew will complete Building 18. Miscellaneous painting in the community will follow. Please contact our office with questions. For the week of…
Read moreRancho El Mirage
Hello Residents For the week of 10/9: Our crew will be onsite finishing up all touch-ups by Wednesday to complete all work in the community. For the week of 9/25: Our crew will be finishing trim painting and prep work…
Read moreOverlook II
Hello Residents For the week of 11/20: Our crew will be finishing iron gates on Monday, and doing any necessary touch-up work on Tuesday and Wednesday. The pool fencing is also expected to be completed on Wednesday. **This will wrap…