Author: April

January 22, 2018 April No Comments

The Foothills – Zone 6

Hello Residents For the week of 4/23: Our crew will be completing the iron in Black Rock midweek. No crews will be onsite for painting until further notice. If your iron was skipped in any previous parcel, please contact our office so we can make arrangements for painting.  For the week of 4/16: Our crew […]

December 11, 2017 April No Comments

Desert Foothills Office Suites

For the week of 1/15: Our crew is painting carports, light poles, and completing necessary touch ups. All painting is expected to be completed on Wednesday. Feel free to call or email with any questions.  For the week of 1/2/2018: Happy New Year! Our crew will complete the painting of Building 1 on Wednesday. Building […]

November 27, 2017 April No Comments

Patrick Ranch

Hello Residents For the week of 12/18: Our crew was able to paint all exterior common area walls and most of the adjoining neighbor walls for Section 2 last week (smaller section on map). All painting is expected to be completed on Monday, 12/18. Feel free to call or email our office with any questions. […]

November 27, 2017 April No Comments

Tesoro at Grayhawk

Hello Residents ATTN: Painting is completed in Tesoro. If you have door edges that were unable to be painted previously, our crew will only be returning 5/26 & 6/2 to paint them. Please contact our office. For the week of 4/30: All buildings that were scheduled to be painted have been completed. We have a […]

November 27, 2017 April No Comments

Sunland Springs Village Garden Condos

Hello Residents All painting in the community has been completed.  For the week of 2/19: Our crew will be completing the exterior of Units 85-93 on Wednesday, weather permitting (wind & rain on Monday delayed progress 1 day). Doors will be painted on Thursday. Please leave your front and back security screens unlocked on 2/21 & […]

November 6, 2017 April No Comments

Asante Park

Hello Residents For the week of 1/29: Our crew will be completing walls by Monday or Tuesday (in PINK). Some homeowners were notified of iron painting being done this week. Our iron crew expects to have all added iron completed by Wednesday 1/31. This will complete all painting in the community. For the week of 1/22: […]

November 6, 2017 April No Comments

Pueblo at Andersen Springs

Hello Residents *Job completed* For the week of 12/4: Our crew will be prepping and painting Building 25 and expect to have to have it completed by Thursday or Friday. They’ll also be painting the front entry and pedestrian gates. This will complete all the work scheduled for painting. Feel free to call or email our […]

October 23, 2017 April No Comments

Villas at Desert Camp

Hello Residents  For the week of 11/5/2018:  We are on our last building this week – Building 10!  Please remove all decor or vegetation from your building and place all patio furniture in the center of your patio or indoors.  Feel free to contact our office with any questions.  WE APPRECIATE YOU AND THANK YOU […]

October 9, 2017 April No Comments

Rovey Farms

Hello Residents For the week of 10/30: **Our crew will be completed with all community painting this Tuesday.** For the week of 10/23: Our crew will be prepping and painting walls (highlighted yellow on map below) on the South side of Emil Rovey Pkwy. Feel free to call or email with any questions.   For […]

October 2, 2017 April No Comments

Cactus Gates

Hello Residents For the week of 10/23: *Our crew will be completing all community painting this week.* The wall facing FLW will complete all the wall painting, and iron in the community wash will be completed by the end of the week as well. Feel free to call or email with any questions. For the […]

September 12, 2017 April No Comments

San Marcos Manor

Hello Residents For the week of 10/23: Our iron crew will be (electrostatic) painting the view fencing in backyards. They are expected to be completed by the end of the week. Please watch for a notice and make sure that any vegetation, wiring, decor, etc are removed from the fencing and that pets are kept inside. […]

September 11, 2017 April No Comments

Kierland Progress Report

Hello Residents For the week of 10/2: Our crew will be painting the common area walls facing 64th St. from Greenway to Acoma Dr. Feel free to call or email with any questions. Painting in the community will be completed this week. For the week of 9/25: Our crew is painting walls off of Acoma […]

August 28, 2017 April No Comments

The Villas at Camelback Crossing

Hello Residents For the week of 9/3: We’ll be closed on Monday for Labor Day. On Tuesday our crew will complete Building 18. Miscellaneous painting in the community will follow. Please contact our office with questions. For the week of 8/27: Painting will begin on Building 18 on Monday (it was power washed and prepped last Friday) […]

July 31, 2017 April No Comments

Rancho El Mirage

Hello Residents For the week of 10/9: Our crew will be onsite finishing up all touch-ups by Wednesday to complete all work in the community. For the week of 9/25: Our crew will be finishing trim painting and prep work on common walls in Section 6 on Monday/Tuesday. The main body color painting of Section […]

July 31, 2017 April No Comments

Overlook II

Hello Residents For the week of 11/20: Our crew will be finishing iron gates on Monday, and doing any necessary touch-up work on Tuesday and Wednesday. The pool fencing is also expected to be completed on Wednesday. **This will wrap up all of the general community painting.** Be advised that door staining will continue after […]