Hello Residents For the week of 12/31: Happy New Year! Our crew will be back Wednesday, January 2nd through Saturday painting the perimeter wall, skipped doors, and balconies. Notices will be placed on appropriate units. This will complete painting in…
Read moreAuthor Archives: April
Iron Oaks at Sun Lakes
Hello Residents For the week of 11/26: Our iron crew will be on-site on Tuesday only to try and paint view fences that were previously skipped. For the week of 10/15: Our crew will be wrapping up the painting in…
Read moreCasa Del Rey
Hello Residents For the week of 11/5: We will have a crew on site on 11/7 to paint monument signs only. For the week of 10/29: Our crew will continuing with the pool clubhouse and surrounding iron through Wednesday. This…
Read moreArroyo Mountain
Hello Residents For the week of 10/29: Our crew will continue with the trim painting on common area walls throughout the community. All walls are expected to be completed on Thursday and this will complete painting in the community. Feel…
Read moreTerramar
Hello Residents! Starting 8/29-8/30: Our iron crew will be onsite to paint iron that was previously skipped due to various reasons. Please contact the HOA office or our office to confirm that iron is cleared, gate is unlocked, you’re ready…
Read moreMoonlight Cove
Hello Residents For the week of 6/17: Our crew will be on site on Friday only to paint iron for homes that were previously skipped. Please remove all vegetation, chicken wire, decor, etc from the iron and please secure your…
Read moreMessina
Hello Residents: For the week of 5/21: Our crew will be completing the iron painting on Tuesday. Please make sure that all vegetation, chicken wiring, etc is removed from the iron so there’s clear access to paint. This will complete…
Read moreThe Foothills Zone 1
Hello Residents For the week of 8/13: Our crew is continuing with the painting or walls and iron in La Montage and expect to be completed with everything there on Wednesday. Iron painting for Cathedral Rock was started on Monday…
Read moreLa Fortina
Hello Residents For the week of 4/9: Our crew will be painting wrought iron for homes facing the park before moving along to common area iron fencing. Gates will be painted on Wednesday which will wrap up all the work…
Read moreFiesta Park Village
Hello Residents Painting is completed. Our crew will return to paint skipped doors and edges. Notices will be left to advise of dates. Feel free to contact our office with any questions. For the week of 7/30: Due to a…
Read moreIsland Palms Apartments
Hello Residents For the week of 6/25: Our crew will be painting the office and carports this week. Please keep an eye out for notices as to which day(s) to move your vehicle for washing/painting. Feel free to contact our…
Read moreCooper Ranch
Hello Residents For the week of 3/5: Our crew will be painting rod iron view fencing this week and expected to have it all completed by Wednesday. Common walls in the community were painted on 3/2. Please leave your side…
Read moreDesert Ridge 2018
Hello Residents For the week of 7/23: Our crew is on site finishing some odds and ends painting and will be completed this week. Please contact our office or FirstService immediately if you’re iron view fencing was unable to be…
Read moreRosegarden Townhouses
Hello Residents For the week of 2/19/2018: Our crew will be painting back entry gates throughout the week. Due to Monday’s rain delay, painting may continue into the week of 2/26. Please leave gates unlocked and remove any decor from…
Read moreEagle Cove
Hello Residents Painting has been completed. For the week of 2/12: All wall painting throughout the community is expected to be completed on Wednesday 2/14/2018. For the week of 2/5: Our crew will be working on painting the trim on…
Read more